Transformer RFQ specification checklist
What to state in a power or distribution transformer enquiry so that supplier quotes can be compared like for like.
How this was prepared
Compiled by Anvilmore from the parameter headings of the general power-transformer standards (IEC 60076-1, IEEE C57.12.00) and the commercial terms screened in Critical Supply diligence. It lists what to state, not what values to choose. Final engineering acceptance remains with the buyer and qualified professionals.
An incomplete enquiry produces quotes that cannot be compared: one supplier assumes outdoor service, another indoor; one prices guaranteed losses, another does not. Use this list to check that your RFQ states each item, or states that it is deliberately left to the bidder.
What to state
A. Application and site
- Duty of the transformer Generator step-up, step-down, distribution or auxiliary.
- Indoor or outdoor installation
- Altitude and ambient temperature range
- Seismic requirement, if any
- Pollution level at the site
- Transport limits Maximum weight, dimensions and route restrictions.
- Available footprint and clearances
B. Electrical ratings
- Rated power for each cooling stage For example ONAN and ONAF.
- High-voltage and low-voltage ratings
- Frequency and number of phases
- Vector group
- Short-circuit impedance
- Tapping range and type On-load or off-circuit.
- Insulation levels Including lightning impulse withstand.
- System fault level and short-circuit withstand requirement
- Loading or overload profile
C. Losses and performance
- Guaranteed no-load losses and load losses
- Loss-capitalisation values used to evaluate bids State them in the RFQ so bidders optimise for the same evaluation.
- Minimum-efficiency rules in the destination market For example, Commission Regulation (EU) No 548/2014 applies to power transformers placed on the EU market.
- Maximum sound level
D. Construction
- Insulating liquid
- Conservator or sealed tank
- Bushings and terminations
- Cooling equipment
- Protection and monitoring accessories
- Corrosion protection
- Nameplate and documentation language
E. Tests and inspection
- Routine tests under the governing standard
- Which type or special tests must be performed, and which may be accepted from existing certificates
- Witnessed factory acceptance test
- Third-party inspection, if required
- Test report format and delivery
F. Standards and compliance
- Governing standard family IEC 60076 series, IEEE C57.12 series or a national adoption.
- Utility or owner specification that applies
- Origin requirements
- Sanctions and export screening of the supplier and the goods
G. Commercial and delivery
- Delivery point and Incoterms 2020 rule
- Lead time stated with its start event and stop event Start: order or drawing approval. Stop: ex-works, delivered or energised. See the Anvilmore note on transformer lead times, linked below.
- Drawing-approval cycle
- Payment milestones
- Warranty period and the event that starts it
- Remedies for delay
- Spares
- Transport, assembly and oil filling Who is responsible and what is priced.
- Quote validity
- Price-adjustment basis
This checklist is not an engineering specification and does not recommend any values. Parameter selection and acceptance belong with the buyer and qualified engineers.
Sources
- IEC 60076-1:2011 Power transformers - Part 1: General, International Electrotechnical Commission. Publication page; the standard itself is paid.
- IEEE C57.12.00 General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers, IEEE Standards Association. Publication page; the standard itself is paid.
- Commission Regulation (EU) No 548/2014 (ecodesign requirements for small, medium and large power transformers), EUR-Lex.
- Incoterms 2020 rules, International Chamber of Commerce.